mark milestones explicitly

This commit is contained in:
Andreas Zweili 2018-12-28 16:03:06 +01:00
parent 50a1437a19
commit d4de8cffe2
1 changed files with 21 additions and 21 deletions

View File

@ -12,13 +12,13 @@
<calendar id="1" name="Default">
<default-week mon="3" tue="3" wed="3" thu="3" fri="3" sat="1" sun="0"/>
<overridden-day-types>
<overridden-day-type id="3">
<interval start="1900" end="2100"/>
</overridden-day-type>
<overridden-day-type id="0">
<interval start="1000" end="1200"/>
<interval start="1300" end="1700"/>
</overridden-day-type>
<overridden-day-type id="3">
<interval start="1900" end="2100"/>
</overridden-day-type>
</overridden-day-types>
<days>
<day date="20181213" type="day-type" id="3"/>
@ -49,19 +49,19 @@
<day date="20181229" type="day-type" id="0"/>
<day date="20190103" type="day-type" id="0"/>
<day date="20181211" type="day-type" id="3"/>
<day date="20181231" type="day-type" id="3"/>
<day date="20190225" type="day-type" id="0"/>
<day date="20190427" type="day-type" id="0"/>
<day date="20181226" type="day-type" id="3"/>
<day date="20190128" type="day-type" id="0"/>
<day date="20190302" type="day-type" id="0"/>
<day date="20181226" type="day-type" id="3"/>
<day date="20190427" type="day-type" id="0"/>
<day date="20190225" type="day-type" id="0"/>
<day date="20190128" type="day-type" id="0"/>
<day date="20181231" type="day-type" id="3"/>
<day date="20190202" type="day-type" id="0"/>
<day date="20190105" type="day-type" id="0"/>
</days>
</calendar>
</calendars>
<tasks>
<task id="1" name="Start Diplomarbeit" note="" work="0" start="20181210T000000Z" end="20181210T000000Z" work-start="20181210T190000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
<task id="1" name="Meilenstein: Start Diplomarbeit" note="" work="0" start="20181210T000000Z" end="20181210T000000Z" work-start="20181210T190000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
<constraint type="must-start-on" time="20181210T000000Z"/>
</task>
<task id="2" name="Initialisierung" note="" work="79200" start="20181210T000000Z" end="20181221T210000Z" work-start="20181210T190000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
@ -105,7 +105,7 @@
</predecessors>
</task>
</task>
<task id="12" name="Initialisierung abgeschlossen" note="" work="0" start="20181221T210000Z" end="20181221T210000Z" work-start="20181221T210000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
<task id="12" name="Meilenstein: Initialisierung abgeschlossen" note="" work="0" start="20181221T210000Z" end="20181221T210000Z" work-start="20181221T210000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
<predecessors>
<predecessor id="1" predecessor-id="11" type="FS"/>
</predecessors>
@ -176,7 +176,7 @@
<predecessor id="1" predecessor-id="26" type="FS"/>
</predecessors>
</task>
<task id="28" name="Analyse abgeschlossen" note="" work="0" start="20190102T150000Z" end="20190102T150000Z" work-start="20190102T150000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
<task id="28" name="Meilenstein: Analyse abgeschlossen" note="" work="0" start="20190102T150000Z" end="20190102T150000Z" work-start="20190102T150000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
<predecessors>
<predecessor id="1" predecessor-id="27" type="FS"/>
</predecessors>
@ -213,7 +213,7 @@
</predecessors>
</task>
</task>
<task id="37" name="Konzeptionierung abgeschlossen" note="" work="0" start="20190110T210000Z" end="20190110T210000Z" work-start="20190110T210000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
<task id="37" name="Meilenstein: Konzeptionierung abgeschlossen" note="" work="0" start="20190110T210000Z" end="20190110T210000Z" work-start="20190110T210000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
<predecessors>
<predecessor id="1" predecessor-id="36" type="FS"/>
</predecessors>
@ -324,7 +324,7 @@
<predecessor id="1" predecessor-id="59" type="FS"/>
</predecessors>
</task>
<task id="61" name="Realisierung abgeschlossen" note="" work="0" start="20190302T170000Z" end="20190302T170000Z" work-start="20190302T170000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
<task id="61" name="Meilenstein: Realisierung abgeschlossen" note="" work="0" start="20190302T170000Z" end="20190302T170000Z" work-start="20190302T170000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
<predecessors>
<predecessor id="1" predecessor-id="60" type="FS"/>
</predecessors>
@ -346,7 +346,7 @@
<predecessor id="1" predecessor-id="64" type="FS"/>
</predecessors>
</task>
<task id="66" name="Ausblick abgeschlossen" note="" work="0" start="20190304T120000Z" end="20190304T120000Z" work-start="20190304T120000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
<task id="66" name="Meilenstein: Ausblick abgeschlossen" note="" work="0" start="20190304T120000Z" end="20190304T120000Z" work-start="20190304T120000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
<predecessors>
<predecessor id="1" predecessor-id="65" type="FS"/>
</predecessors>
@ -382,21 +382,21 @@
<constraint type="must-start-on" time="20190301T000000Z"/>
</task>
</task>
<task id="77" name="Diplomarbeit abgeben" note="" work="0" start="20190318T000000Z" end="20190318T000000Z" work-start="20190318T190000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
<task id="77" name="Meilenstein: Diplomarbeit abgeben" note="" work="0" start="20190318T000000Z" end="20190318T000000Z" work-start="20190318T190000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
<constraint type="must-start-on" time="20190318T000000Z"/>
</task>
<task id="78" name="Pr&#xE4;sentation" note="" work="0" start="20190402T000000Z" end="20190402T000000Z" work-start="20190402T190000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
<task id="78" name="Meilenstein: Pr&#xE4;sentation" note="" work="0" start="20190402T000000Z" end="20190402T000000Z" work-start="20190402T190000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
<constraint type="start-no-earlier-than" time="20190402T000000Z"/>
<predecessors>
<predecessor id="1" predecessor-id="77" type="FS"/>
</predecessors>
</task>
<task id="79" name="Ausstellung" note="" work="86400" start="20190331T000000Z" end="20190428T120000Z" work-start="20190331T100000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
<task id="79" name="Ausstellung" note="" work="86400" start="20190402T000000Z" end="20190427T150000Z" work-start="20190402T190000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
<constraint type="must-start-on" time="20190427T000000Z"/>
<task id="80" name="Ausstellung vorbereiten" note="" work="86400" duration="259200" start="20190331T000000Z" end="20190428T120000Z" work-start="20190331T100000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-duration">
<constraint type="start-no-earlier-than" time="20190331T000000Z"/>
<task id="80" name="Ausstellung vorbereiten" note="" work="86400" duration="216000" start="20190402T000000Z" end="20190427T150000Z" work-start="20190402T190000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-duration">
<constraint type="start-no-earlier-than" time="20190402T000000Z"/>
</task>
<task id="81" name="Arbeit ausstellen" note="" work="0" start="20190427T000000Z" end="20190427T000000Z" work-start="20190427T100000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
<task id="81" name="Meilenstein: Arbeit ausstellen" note="" work="0" start="20190427T000000Z" end="20190427T000000Z" work-start="20190427T100000Z" percent-complete="0" priority="0" type="milestone" scheduling="fixed-work">
<constraint type="must-start-on" time="20190427T000000Z"/>
</task>
</task>
@ -406,7 +406,7 @@
<resource id="1" name="Andreas Zweili" short-name="AZ" type="1" units="0" email="" note="" std-rate="60" calendar="1"/>
</resources>
<allocations>
<allocation task-id="80" resource-id="1" units="33"/>
<allocation task-id="80" resource-id="1" units="40"/>
<allocation task-id="69" resource-id="1" units="100"/>
<allocation task-id="60" resource-id="1" units="100"/>
<allocation task-id="35" resource-id="1" units="100"/>